Ranking the prevalence of construction cost overrun risk factors in completion of public-private partnership projects
Pamela Akinyi Oyieyo ORCID ↗ · Charles M Rambo ORCID ↗ · Anne Ndiritu ORCID ↗
International Journal of Research in Business and Social Science · 2020 · Vol. 9 / Issue 5 · 351-356
Publication metrics
External links open provider records or DOI searches. Provider counts are not combined. Mendeley readership measures saves, not citations.
Dimensions
Live provider badge. If unavailable, use the Dimensions link above.
Observed 21 Oct 2026, 07:22 UTC
Observed 22 Oct 2026 01:06 UTC
Observed 22 Oct 2026 01:06 UTC
OpenAlex and Mendeley observations refresh on article visits, at most once per 24 hours. Unavailable data is not zero. Google Scholar opens a DOI search.
Citations received by this article, grouped by the year of the citing work. Crossref and OpenAlex lifetime totals remain separate in Publication metrics.
2017–2026 Annual history last updated:
Citations received
OpenAlex · year of the citing work
Hover over a year or focus the chart and use arrow keys to inspect values.
2017–2026 annual-history window. 2026 is year to date. Unknown years have gaps.
View data & coverage
2026 is incomplete. Within a successfully fetched ten-year window, omitted years mean zero. Years beyond a saved observation’s window remain unknown (—). Older citations are excluded, so this chart’s sum may differ from the OpenAlex lifetime total. The date above belongs to this annual history; an unsuccessful refresh keeps the previous observation.
Abstract
The purpose of the study was to identify and rank the prevalence and severity of risk factors construction cost overrun in Public-Private Partnership projects using a case study of Sondu-Miriu Hydroelectric Power Project in Kisumu County, Kenya. This study adopted a descriptive design and collected quantitative data analysed quantitatively using descriptive statistics. In total, 85 persons were identified to have taken part in the management and implementation of the study from whom a sample size of 71 participants was obtained. Questionnaires were emailed to the participants providing details of the study and requesting their participation. The study ranked the risk factors based on prevalence and severity from most prevalently severe to least prevalently severe as design changes, emerging tasks affecting delivery, construction task breakdown structure, design variations and failure of contractors to complete different tasks. Thus, stakeholders should participate fully in the project from design to avoid design changes leading to cost overrun. During implementation, the contractor and construction manager should device mechanisms to anticipate changes in the political environment as such changes determines government policies and decisions affecting the project funding, design and scope.
Keywords: {'name': 'Prevalence, Cost Overrun, Risk Factors, Construction Projects, Public-Private Partnership'}
Authors & affiliations
Pamela Akinyi Oyieyo
Affiliation not supplied
Charles M Rambo
Affiliation not supplied
Anne Ndiritu
Affiliation not supplied
Deposited references
Supplied references, not a list of publications citing this article.
DOI: 10.1061/(ASCE)0733-9364(2007)133:12(918)
DOI: 10.1061/(ASCE)0733-9364(2007)133:12(918)
DOI: 10.1108/IJMPB-10-2016-0078
DOI: 10.1061/(ASCE)IS.1943-555X.0000035
Anastasopoulos, P.Ch., Volovski, M., Pradhan, S., Islam, M., &Labi, S. (2011). Public Private Partnerships (PPPs) in Highway Reconstruction, Rehabilitation, and Operations. Prepared for the US Department of Transportation, USDOT Region V Regional University Transportation Center Final Report, NEXTRANS Project No. 045PY02. URL: https://www.purdue.edu/discoverypark/cav/nextrans/completed-projects/docs/Final%20Report%20045.pdf
DOI: 10.1061/(ASCE)CO.1943-7862.0000225
DOI: 10.5703/1288284313134
DOI: 10.1061/(ASCE)CO.1943-7862.0000743
DOI: 10.1016/j.ijproman.2018.03.004
DOI: 10.3846/1648715X.2012.688774
DOI: 10.1080/0144164032000080494a
DOI: 10.1016/S0263-7863(02)00055-8
DOI: 10.1061/(ASCE)0733-9364(2007)133:6(404)
DOI: 10.1061/(ASCE)CO.1943-7862.0000084
Ichimura, M. (2003). Urbanization, Urban Environment and Land Use: Challenges and Opportunities. An Issue Paper. In Proceedings of the Asia-Pacific Forum for Environment and Development, Expert Meeting, Guilin, China,23, URL: https://pdfs.semanticscholar.org/2efc/f8efedadb4b71be7dab44de27fe95aac2986.pdf?_ga=2.242048386.1052935163.1599140540-1690217655.1598884376
DOI: 10.1111/j.1540-6210.2008.01974.x
DOI: 10.1080/0144619042000326710
DOI: 10.2307/41166480
DOI: 10.3141/1885-06
DOI: 10.1016/j.landurbplan.2004.04.002
DOI: 10.1016/S0263-7863(03)00005-X
Mousa, J. H. A. (2005).Risk Management in Construction Projects from Contractors andOwners’ perspectives.Unpublished MSc. Thesis. Palestine: The Islamic University of Gaza-Palestine. https://www.coursehero.com/file/36013336/Risk-Managementdocx/
Mweresa, J. O. (2013). Impact of Increasing Building Construction Costs on Effective Implementation of Public Projects: A Case Study of the Projects Initiated By the Ministry Of Public Works within Nairobi County – Kenya. Unpublished Bachelor’s Project, University of Nairobi. http://erepository.uonbi.ac.ke/bitstream/handle/11295/28925/Talukhaba_An%20investigation%20into%20factors%20causing%20construction%20project%20delays%20in%20Kenya.pdf?sequence=3&isAllowed=y
DOI: 10.17265/1537-1506/2015.07.001
Osipova, E. (2008). Risk management in construction projects: a comparative study of thedifferent procurement options in Sweden (Unpublished master's thesis). Lic.-avh. (sammanfattning) Luleå: Luleå tekniskauniv. URL: https://www.diva-portal.org/smash/get/diva2:999456/FULLTEXT01.pdf
DOI: 10.3390/su11226455
Bird’s Nest Stadium Project. (2009). Available online: https://www.sohu.com/a/142496023_798724 (accessed on 22 May 2020).
Tipili, G.L., &IIyasu, M.S. (2014). Evaluating the impact of risk factors on construction projects cost in Nigeria. The International journal of Engineering and Science (IJES). 3(6), 10-15.ISSN (e): 2319 – 1813 ISSN. URL: https://pdfs.semanticscholar.org/8aac/e9a33197006eea1dab23063d9f145ab79081.pdf
DOI: 10.1016/j.ijproman.2018.10.008
DOI: 10.1080/0042098992412
DOI: 10.1111/j.0309-1317.2004.00527.x
Zhu, K., & Lin, L., (2004). A Stage – By – Stage Factor Control Frame Work for Cost Estimation of Construction Projects, Owners Driving Innovation International Conference. http:/ flybjerg. Plan.aau.dk / JAPAASPUBLISHED.pelf.
DOI: 10.1108/13664380810898131