The impact of financial aspect on procurement procedures in achieving sustainable public procurement: A case of Zanzibar urban services project
Asha Ramadhan · William Gomera ORCID ↗
International Journal of Research in Business and Social Science · 2022 · Vol. 11 / Issue 10 · 265-276
Publication metrics
External links open provider records or DOI searches. Provider counts are not combined. Mendeley readership measures saves, not citations.
Dimensions
Live provider badge. If unavailable, use the Dimensions link above.
Observed 21 Oct 2026, 07:22 UTC
Observed 21 Oct 2026 07:22 UTC
Observed 22 Oct 2026 01:25 UTC
OpenAlex and Mendeley observations refresh on article visits, at most once per 24 hours. Unavailable data is not zero. Google Scholar opens a DOI search.
Citations received by this article, grouped by the year of the citing work. Crossref and OpenAlex lifetime totals remain separate in Publication metrics.
2017–2026 Annual history last updated:
Citations received
OpenAlex · year of the citing work
Hover over a year or focus the chart and use arrow keys to inspect values.
2017–2026 annual-history window. 2026 is year to date. Unknown years have gaps.
View data & coverage
2026 is incomplete. Within a successfully fetched ten-year window, omitted years mean zero. Years beyond a saved observation’s window remain unknown (—). Older citations are excluded, so this chart’s sum may differ from the OpenAlex lifetime total. The date above belongs to this annual history; an unsuccessful refresh keeps the previous observation.
Abstract
The current study examined the impact of financial aspects in achieving sustainable public procurement at the Zanzibar Urban Services Project. To achieve this objective, the study used a questionnaire and documentary review checklist to collect data on identifying the impact of financial aspects on sustainable public procurement. The study used a case study design using Zanzibar Urban Services Project. Both primary and secondary data were collected through questionnaires and documentary reviews. The researcher employed the probability sampling technique specifically stratified sampling technique to sample 107 out of 153 individuals from the field and content analysis for documentary review. Descriptive analysis was used to analyse preliminary data and lastly multiple regression analysis modals was used to measure the relationship among variables. Study results indicated that in spite of the contribution of financial aspects in procurement, there is a challenge of undermining the emphasis of other non-financial aspects in procurement procedures. It was also confirmed that there is a need of balancing between financial, social and environmental aspects which are argued to achieve sustainable public procurement.
Keywords: {'name': 'Procurement Procedures'}, {'name': 'Financial aspect'}, {'name': 'Sustainable Public Procurement'}
Authors & affiliations
Asha Ramadhan
Affiliation not supplied
William Gomera
Affiliation not supplied
Deposited references
Supplied references, not a list of publications citing this article.
DOI: 10.1016/j.ijproman.2009.03.005
DOI: 10.17148/IARJSET.2016.3420
Alson, G. S. (2018). Tanzania-AFRICA-P162538-Mainland and Zanzibar National Audit Offices Capacity Building Project-Procurement Plan.
Andabaka, A., & Serti?, M. B. (2020). Promoting Sustainable Development via Public Procurement: Is the European Union Leading by example?. In Proceedings of FEB Zagreb International Odyssey Conference on Economics and Business 2(1) 721-739). The University of Zagreb, Faculty of Economics and Business.
DOI: 10.1177/0956797617723724
Ayodele, E. O. (2011). Abandonment of construction projects in Nigeria: causes and effects. Journal of Emerging Trends in Economics and Management Sciences, 2(2) 142-145.
DOI: 10.1061/(ASCE)ME.1943-5479.0000443
DOI: 10.1016/j.jom.2015.10.003
DOI: 10.1080/15623599.2018.1484859
DOI: 10.1002/pssa.200824288
DOI: 10.1504/IJPM.2009.023407
DOI: 10.1007/s11115-019-00443-7
Bosch, M., Kemperman, M., & Raes, S. (2012). Sustainable Procurement and International Financial Institutions. In Seminar on Sustainable Public Procurement and Multilateral Development Banks, March ( 22).
Brahim, F. J., Abada, O., & Muhindo, A. (2014). Implementation of procurement planning in parastatal organizations: A case study of Tanzania Postal Bank Head Quarters in Dar-es-salaam. International Journal of Academic Research in Management, 3(3) 226-232.
DOI: 10.1007/s10551-006-9071-z
CAG. (2019). The annual general report of the Controller Audit General on the financial statement of the Central Government for the financial year ended 30th June, 2018. The United Republic of Tanzania.
Creswell, J. W., & Creswell, J. D. (2017). Research design: Qualitative, quantitative, and mixed methods approaches. Sage publications.
DOI: 10.20525/ijrbs.v11i8.2043
DOI: 10.20525/ijrbs.v11i8.2198
Eberhard, A., Kolker, J., & Leigland, J. (2014). South Africa's renewable energy IPP procurement Program: Success factors and lessons.
DOI: 10.1016/j.ijproman.2010.01.003
DOI: 10.1108/JOPP-14-02-2014-B001
DOI: 10.1017/CBO9780511521706
DOI: 10.1108/JOPP-15-01-2015-B003
DOI: 10.1007/978-3-319-05542-8_15-1
DOI: 10.3390/su13042116
DOI: 10.1108/IJPSM-09-2019-0233
DOI: 10.2991/aebmr.k.200502.089
Jafari, S. (2017). Assessment of tendering procedures in public organizations in Tanzania: a case of Tanzania Revenue Authority (TRA) in Dodoma. The University of Dodoma.
Kagiri, D., & Wainaina, G. (2017). Time and Cost Overruns in Power Projects in Kenya: A Case Study of Kenya Electricity Generating Company Limited. ORSEA JOURNAL, 3(2.
DOI: 10.15764/MR.2014.01004
DOI: 10.3846/btp.2014.529
DOI: 10.18034/abcjar.v3i2.33
DOI: 10.22363/2313-2337-2022-26-1-149-170
DOI: 10.5130/ajceb-cs.v1i2.3166
Kothari, C. (2012). Research methodology: An introduction. Research Methodology: Methods and Techniques, 9 No.) 418.
DOI: 10.1007/978-3-030-60929-0_78
DOI: 10.1007/s10669-022-09854-2
DOI: 10.4324/9781315108049
DOI: 10.18060/17686
DOI: 10.1061/(ASCE)CO.1943-7862.0000573
DOI: 10.1057/palgrave.jibs.8490068
Maxwell, J. A. (2012). Qualitative research design: An interactive approach” ( 41), Sage publications.
DOI: 10.1108/JOPP-15-02-2015-B003
Mrope, N. P. (2018). Determinants of performance of procurement departments in public entities in Tanzania. JKUAT-COHRED.
Naluyima, H. O., Keefa, K., & Kampumure, J. (2016). The Effect of Procurement Management on Project Performance: A Case of the Uganda Millennium Science Initiative Project. Uganda Management Institute.
DOI: 10.4324/9781315172231
Okori, F. (2018). Analyzing contractor procurement criteria as a key factor in the successful completion of road construction projects in Uganda. Makerere University.
DOI: 10.1108/IJPSM-10-2015-0173
DOI: 10.4102/jef.v7i4.386
Sindano, G. (2020). Zanzibar Urban Services Project (ZUSP) for the Period Ended 30th June 2019 Audit Report: The World Bank.
DOI: 10.3390/su13179605
DOI: 10.22610/jebs.v4i1.300
DOI: 10.1080/01441647.2013.854281
DOI: 10.1016/j.ijpe.2012.01.008
DOI: 10.3846/1611-1699.2008.9.181-187