Factors affecting time and cost in road construction projects at a South African municipality
Monwabisi Siwakhile Xegwana ORCID ↗ · Michael Twum-Darko · Robertson K. Tengeh ORCID ↗
International Journal of Research in Business and Social Science · 2024 · Vol. 13 / Issue 6 · 405-413
Publication metrics
External links open provider records or DOI searches. Provider counts are not combined. Mendeley readership measures saves, not citations.
Dimensions
Live provider badge. If unavailable, use the Dimensions link above.
Observed 21 Oct 2026, 07:22 UTC
Observed 21 Oct 2026 07:22 UTC
Observed 22 Oct 2026 01:30 UTC
OpenAlex and Mendeley observations refresh on article visits, at most once per 24 hours. Unavailable data is not zero. Google Scholar opens a DOI search.
Citations received by this article, grouped by the year of the citing work. Crossref and OpenAlex lifetime totals remain separate in Publication metrics.
2017–2026 Annual history last updated:
Citations received
OpenAlex · year of the citing work
Hover over a year or focus the chart and use arrow keys to inspect values.
2017–2026 annual-history window. 2026 is year to date. Unknown years have gaps.
View data & coverage
2026 is incomplete. Within a successfully fetched ten-year window, omitted years mean zero. Years beyond a saved observation’s window remain unknown (—). Older citations are excluded, so this chart’s sum may differ from the OpenAlex lifetime total. The date above belongs to this annual history; an unsuccessful refresh keeps the previous observation.
Abstract
The South African construction sector is confronted by significant obstacles, particularly concerning cost overruns and project delays within the road construction sphere. This research sought to investigate the factors impacting cost and duration in road construction projects under the purview of a KwaZulu-Natal municipality. A qualitative research approach was adopted to explore this phenomenon. A sample size of 27 participants was selected from a population of 171 for in-depth semi-structured interviews. Critical determinants of cost overruns and delays were identified as ineffective communication, suboptimal procurement processes, deficient stakeholder management, and shortcomings in project execution and personnel capabilities. This study offers valuable insights into the relationship between cost, time, and the successful delivery of road projects within the local government context. By illuminating these factors, the research contributes to a deeper theoretical understanding, informs evidence-based policy development, and provides actionable recommendations for enhancing project management practices.
Authors & affiliations
Monwabisi Siwakhile Xegwana
Affiliation not supplied
Michael Twum-Darko
Affiliation not supplied
Robertson K. Tengeh
Affiliation not supplied
Deposited references
Supplied references, not a list of publications citing this article.
DOI: 10.5267/j.jpm.2023.6.002
DOI: 10.46743/2160-3715/2018.2994
Alfakhri, A., Ismail, A., Khoiry, M. A., Arhad, I., & Irtema, H. I. M. (2017). A conceptual model of delay factors affecting road construction projects in Libya. Journal of Engineering Science and Technology, 12(12), 3286-3298.
Algozzine, B., & Hancock, D. (2017). Doing case study research: A practical guide for beginning researchers. Teachers College Press.
DOI: 10.30880/ijscet.2020.11.02.025
DOI: 10.5130/AJCEB.v21i4.7858
Alzoubi, H. M. (2022). BIM as a tool to optimize and manage project risk management. International Journal of Mechanical Engineering, 7(1), 6307-6323.
DOI: 10.35940/ijeat.B3880.129219
DOI: 10.47672/ijpm.1638
DOI: 10.3390/ijerph17114110
DOI: 10.47852/bonviewJCCE2202272
DOI: 10.11648/j.jccee.20220703.13
Choge, J. K., & Muturi, W. M. (2014). Factors affecting adherence to cost estimates: A survey of construction projects of Kenya National Highways Authority. International Journal of Social Sciences and Entrepreneurship, 1(11), 689-705.
DOI: 10.1016/j.ijpe.2020.107955
DOI: 10.46743/2160-3715/2016.2243
DOI: 10.1108/JEDT-04-2021-0211
DOI: 10.1108/JEDT-11-2015-0075
DOI: 10.1016/j.heliyon.2021.e06826
DOI: 10.1353/csd.2007.0003
Harrison, H., Birks, M., Franklin, R., & Mills, J. (2017, January). Case study research: Foundations and methodological orientations. Forum Qualitative Sozialforschung/Forum: Qualitative Social Research, 18(1).
DOI: 10.3390/app10165506
DOI: 10.35942/jbmed.v3i1.166
DOI: 10.2174/18744478-v16-e2208190
DOI: 10.1080/20476965.2017.1403674
DOI: 10.56201/wjfir.v6.no1.2022.pg49.61
Maxwell, J. A. (2012). Qualitative research design: An interactive approach. Sage Publications.
DOI: 10.29121/granthaalayah.v7.i2.2019.990
DOI: 10.31272/jeasd.27.4.7
DOI: 10.1080/13814788.2017.1375091
DOI: 10.1016/j.ijpe.2021.108260
DOI: 10.32738/JEPPM.201401.0003
Oluwajana, S. M., Ukoje, J. E., Okosun, S. E., & Aje, I. O. (2022). Factors affecting time and cost performance of road construction projects in Nigeria. African Journal of Applied Research, 8(1), 72-84. http://dx.doi.org/10.26437/ajar.03.2022.5
Patton, M. Q. (2014). Qualitative research & evaluation methods: Integrating theory and practice. SAGE Publications.
DOI: 10.1177/1049732317697102
DOI: 10.5772/intechopen.95009
DOI: 10.1088/1757-899X/1255/1/012011
DOI: 10.5267/j.jpm.2023.5.001
DOI: 10.1007/978-981-19-4739-1_47
DOI: 10.21315/jcdc2020.25.1.7
DOI: 10.1061/(ASCE)CP.1943-5487.0000262
Tshering, Y., Wangmo, S., Choden, R., & Lhendup, T. (2020). Factors affecting time overrun in construction projects in Bhutan. Journal of Education and Practice, 11(29), 1-7.
DOI: 10.18820/24150487/as27i1.5
DOI: 10.1177/03611981221087229
DOI: 10.30880/ijie.2018.10.09.032
Vahed, F. (2022). Causes and effects of delays in road construction projects in South Africa (Master's thesis, Faculty of Engineering and the Built Environment).
DOI: 10.1186/s12874-018-0594-7
DOI: 10.3390/app11125531
DOI: 10.5267/j.jpm.2023.7.001